Progress billing guides

Subcontractor Progress Billing Invoice Builder

Build an itemized progress billing package with a current payment request and accounting import.

How to apply it

  1. Match the application number and PO or contract reference to your GC’s instructions.
  2. Review the SOV and approved change amounts before calculating the invoice total.
  3. Use the ZIP’s CSV to stage cost-code and line totals for the accounting import.

Worked example

A gross movement of $32,000, current withholding of $1,600 and an approved $400 release produce a $30,800 current request.

Open the draw workbench

Frequently asked questions

What is the difference between an invoice and a pay application?

A pay application documents how the requested amount was earned. Use the corresponding invoice if your GC also requires its own accounts-payable document.