How to apply it
- Use one unique cost code for each measurable scope.
- Compare base schedule values against the signed subcontract before adding approved modifications.
- Keep a copy of the issued Excel register with each monthly package.
Worked example
A $48,000 fire protection line with $16,000 prior work, $9,500 current work and $2,000 stored shows $27,500 to date and $20,500 remaining.