Partial Retainage Release on a Progress Draw

Record a contract-authorized partial release without losing the line-level balance owed.

How to apply it

  1. Confirm release approval and the SOV lines it applies to.
  2. Enter the original held balance and this period’s release for each affected line.
  3. Verify the retainage ledger and current payment request together.

Worked example

If $9,400 was held and this draw releases $3,500 with no new withholding, the balance is $5,900 and the current request includes the $3,500 release.

Open the draw workbench

Frequently asked questions

What happens if a release exceeds the retained balance?

The workbench flags negative retainage and blocks a clean export until the line is corrected.