How to apply it
- Use the latest approved schedule and list pending changes in the change log.
- Compare earned-to-date value by line, including eligible materials still stored.
- Correct the affected lines and review the net current request again.
Worked example
A $30,000 line with $24,000 prior work, $4,700 new work and $2,100 stored is $800 over the current schedule.