Progress billing guides

Prevent Overbilling on a Construction Draw

Find SOV lines where prior work, this period’s work and stored materials exceed the approved scheduled amount.

How to apply it

  1. Use the latest approved schedule and list pending changes in the change log.
  2. Compare earned-to-date value by line, including eligible materials still stored.
  3. Correct the affected lines and review the net current request again.

Worked example

A $30,000 line with $24,000 prior work, $4,700 new work and $2,100 stored is $800 over the current schedule.

Open the draw workbench

Frequently asked questions

Can an underbilled line offset an overbilled line?

The workbench checks each line independently so an overbilled scope remains visible even if the project total appears within budget.