Plumbing Progress Billing Template

Create a plumbing pay application covering underground work, rough-in, fixtures and inspections.

How to apply it

  1. Set separate codes for rough-in, fixtures and final testing.
  2. Check that stored fixtures and installed fixtures are counted once.
  3. Record approved reroutes as change orders linked to the affected scope.

Worked example

A $14,800 fixture line can show $3,200 installed and $4,900 still stored for the same cutoff while keeping each amount visible.

Open the draw workbench

Frequently asked questions

Can I carry plumbing change orders through multiple applications?

Yes. Keep approved applied changes in the register for the revised schedule and log pending items separately.