Electrical Progress Billing Template

Prepare an electrical subcontractor draw with cost codes for rough-in, gear, feeders, devices and testing.

How to apply it

  1. Split major electrical packages into measurable cost codes.
  2. Reconcile gear and fixture deliveries against their stored schedules.
  3. Match approved panel or feeder scope changes to the corresponding code.

Worked example

Switchgear with a $26,400 eligible recorded value can be tracked in a gear line while rough-in stays in its own installed-work line.

Open the draw workbench

Frequently asked questions

Can a gear delivery and its installation appear in separate draws?

Yes. Record storage and installation in their respective periods and carry forward prior stored amounts.