Contractor Retainage Calculator

Calculate line-specific withholding, a step-down rate and partial release for a contractor progress draw.

How to apply it

  1. Bring forward the prior retained amount from the previous certificate.
  2. Enter contract-authorized retainage rates and any current step-down.
  3. Check the ending balance for over-release before issuing the draw.

Worked example

With $2,600 held before this draw, $800 withheld now and an approved $1,200 release, the new retained balance is $2,200.

Open the draw workbench

Frequently asked questions

Can each scope use a different rate?

Yes. Each SOV line can use its own base rate, a lower current rate, and a separate release amount.